Body parts back on. Sooo close.
My punch list .... really for myself, in no particular order. Still a lot to tidy up. My goal was Jan. 1st - not likely.
DONE. Replace engine side covers w/ gaskets.
DONE. Install K & N filters.
DONE. Install breather hose.
DONE. Install brake arm rod/spring.
DONE. Find/install new petcock (my new w/ hose fitting faces aft and hits the CR26s).
DONE. Wire up start push button switch.
DONE. Purchase/install bar end mirrors.
DONE. Hook up tach wire (yellow from Dyna 2000 bundle).
DONE. Hook up oil pressure and neutral switch wires.
DONE. Install brake pedal return spring (re-zinc).
DONE. Install fuel line.
DONE. Install and crimp spark plug wires.
Kinda DONE. Program m-unit (leaving settings in default mode until bike is running).
DONE. Figure out advance setting for Dyna 2000.
Adjust setting on shocks.
DONE. Install speedo magnet.... and calibrate (not done).
DONE. Bolt up front sprocket retainer.
DONE. Connect shift lever on left rearset.
Synch carbs after start up.
Re-check valve adjustment.
Cut, solder and install throttle cables.
DONE. Cut down and connect clutch cable (too long).
Weld SS bracket mount to muffler (when received).
FAIL. Install headers upon receipt from ceramic coater. Installing instead Mac 4-1 w/ Cone 12" shorty for now.
DONE. Fill w/break in oil.